Finnsementti carrying out plant upgrades to meet 2030 CO2 reduction targets

Finnsementti carrying out plant upgrades to meet 2030 CO2 reduction targets

Finnsementti is carrying out upgrades to its two integrated cement plants as part of its sustainability targets to 2030. The subsidiary of Ireland-based CRH is installing new main burner equipment at its Lappeenranta plant with completion scheduled for mid-2023. The project is intended to allow the plant to increase its use of alternative fuels. The company’s Parainen plant is replacing its satellite coolers with a grate cooler with completion scheduled for the spring of 2024. This work is expected to decrease the plant’s emissions by 10%. Overall the group is preparing to decrease its CO2 emissions by 30% by 2030 compared to 2021 levels.